ENTEL Wire

The complete record of the US nuclear buildout.

Every projectBuying opportunityBusiness relationship

New build

Two companies have asked the NRC to let them start site work before their permits are decided, more than eight months apart.

Source
Federal Register, 8 October 2026
Earliest possible permit
19 November 2026

Why it matters

A limited work authorization moves the date a site mobilizes away from the date the permit is decided. For the Palisades plant in Michigan, the earliest a permit can issue is 19 November 2026.

SMR, LLC filed a phased construction permit application for a dual-unit SMR-300 at Palisades in Michigan. Blue Energy filed one for a BWRX-300 at Victoria, Texas. Both ask to start site work before the permit is decided.

A phased construction permit application arrives in parts; Part 1 carries the limited work authorization request.

Palisades is more than eight months ahead: filed 31 December 2025, docketed 27 February 2026. Blue Energy filed 15 September 2026 and is not docketed; the NRC says later notices will say whether it is.

Palisades has an earliest permit date, set by rule. Under 10 CFR 50.43(a)(3) the notices run four consecutive weeks, then no license for four more. The series began 1 October 2026, the fourth notice publishes 22 October 2026, and the bar lifts 19 November 2026.

SAME INSTRUMENT, OPPOSITE ENDS OF THE PROCESS Phased construction permit, with a limited work authorization request Palisades Energy Center Covert, Michigan Pioneer Units 1 and 2 Two SMR-300 Dockets 50-616, 50-617 Blue Energy Center Victoria, Texas Port of Victoria Unit 1 One BWRX-300 Docket 99902137 DOCKETED 27 FEB 2026 · IN REVIEW TENDERED 15 SEP 2026 · NOT DOCKETED ENTEL, read off the Federal Register, 20 October 2026
Filed more than eight months apart and reported together. ENTEL analysis of Federal Register notices 2026-20626, 2026-21049 and 2026-20678.

In the document

  • No license will be issued by the NRC prior to the giving of these notices and until 4 weeks after the last notice is published in the Federal Register.
    10 CFR 50.43(a)(3)
  • Subsequent Federal Register notices will address the acceptability of the tendered application for docketing and opportunities for participation of the public during the course of the staff's review.
    Federal Register 2026-20678, the Blue Energy notice of 8 October 2026

What to watch

Blue Energy intends to file the full construction permit application within 18 months of 15 September 2026, by March 2028.

The documents

This item was read off the documents above. ENTEL does not run an item it cannot source.