Restarts

The NRC issued an exigent license amendment letting Palisades Energy use an alternate method to free a fuel assembly that tilted during core reload.

Source
Federal Register, 22 October 2026
Hearing requests due
December 21, 2026

Why it matters

A hearing request or petition to intervene is due December 21, 2026, and the amendment's one-time fuel-handling procedure stays in effect until the assembly reaches the spent fuel pool.

Palisades Energy began reloading fuel on August 30, 2026, when assembly DD41 tilted in core location H-1. The NRC issued Amendment No. 283 to the operating license on October 13, 2026, to allow its removal using different equipment.

Palisades Energy entered Mode 6 refueling and began loading fuel into the reactor vessel on August 30, 2026. During core reload, fuel assembly DD41 was placed into core location H-1 and tilted after release by the refueling machine, coming to rest at roughly a 30-degree angle, its lower tie plate in H-1 and its upper tie plate leaning against the core shroud.

PNP asked for the change by letter dated September 30, 2026. The NRC issued Amendment No. 283 to license DPR-20 on October 13, 2026, revising the facility's safety analysis report on a one-time basis so Palisades could move DD41 to the spent fuel pool by different equipment and a different path.

In the document

  • The amendment was issued on October 13, 2026. A request for a hearing or petitions for leave to intervene must be filed by December 21, 2026.
    Federal Register 2026-21594, DATES

What to watch

A hearing request or petition to intervene on the amendment is due December 21, 2026.